SCC Scheduling conditions

SegmentOptAtMax 9

To specify scheduling conditions.

Elements

PositionElementNameRequirementTypeMin/MaxRepeat
10
4017Delivery plan commitment level codeMandatoryID1/3AtMax 1
20
4493Delivery instruction codeOptID1/3AtMax 1
30
C329Pattern descriptionOptAtMax 1
10
2013Frequency codeOptID1/3Exact 1
20
2015Despatch pattern codeOptID1/3Exact 1
30
2017Despatch pattern timing codeOptID1/3Exact 1

Element Details

ID4017NameDelivery plan commitment level codeLength1/3Position10TypeIDRequirementMandatoryCodes
  • <>10
    Indicates that the scheduling information is for immediate execution.
  • <>17
    The maximum amount that the process was designed to accommodate.
  • <>6
    Capacity is available to meet the requested scheduling demands.
  • <>21
    The contracted amount that the process was designed to accommodate over a specific period of time.
  • <>8
    All related schedule information refers to a special demand.
  • <>15
    Initial confirmation of a material requirement.
  • <>4
    An estimate of future requirements based on trends and actual information.
  • <>23
    Await non-edi instruction before shipping.
  • <>3
    Authorizes the manufacturer to order material required for manufacturing specified goods.
  • <>24
    The buyer's commitment is the one defined in the commercial agreement.
  • <>19
    The preliminary version of a product or service.
  • <>13
    The possibility and magnitude of a schedule fluctuation.
  • <>16
    The highest attainable amount.
  • <>1
    Indicates that the scheduling information is a firm commitment.
  • <>26
    Indicates that the scheduling information is a proposal.
  • <>11
    Initial products required in advance of the normal production process.
  • <>14
    The usual amount that a manufacturing facility will use over a specified duration.
  • <>7
    All related schedule information refer to a promotion.
  • <>20
    Product level that is set aside as protection in the event of a work stoppage.
  • <>2
    Authorizes the supplier to start the manufacturing of goods.
  • <>9
    The user can interpret the meaning of the values from information exchanged previously.
  • <>18
    The anticipated amount that the process was designed to accommodate over a specific period of time.
  • <>12
    An estimate of future requirements.
  • <>22
    Deliver to schedule separately supplied.
  • <>5
    Part of a consignment which was not delivered when the original delivery was made.